Building and site concrete for a new auto service center — footings, below-grade service pits and walls, slabs on grade and deck, plus site pavement and pads.
80
Takeoff line items
2
Plan sheets marked
3
Workbook tabs
$250K – $500K
Package size
Colour-coded takeoff markups from the delivered plan set. Click a sheet to enlarge.
5,947 SF
Slab on grade
98.6 CY
Footing & wall concrete
1,876 SF
Concrete pavement
13,137 LB
Rebar
18 summary lines rolled up from 80 detailed takeoff items. Measured quantities, before waste.
01Wall footings
| Item | Quantity |
|---|---|
| Concrete | 53.3 CY |
| Rebar | 4,768 LB |
| Formwork | 499 SFCA |
02Slabs
| Item | Quantity |
|---|---|
| 6" slab on grade, WWF reinforced | 4,452 SF |
| 12" slab on grade | 1,495 SF |
| 3" slab on composite metal deck | 1,123 SF |
| 4" porous fill | 74.9 CY |
| 10 mil vapor barrier | 5,947 SF |
| Slab rebar | 3,531 LB |
03Thickened edges & concrete walls
| Item | Quantity |
|---|---|
| Thickened edge concrete | 5.1 CY |
| Wall concrete | 40.2 CY |
| Wall rebar | 4,145 LB |
| Wall formwork | 2,582 SFCA |
04Site concrete
| Item | Quantity |
|---|---|
| 7" 4000 PSI concrete pavement | 1,876 SF |
| 6" dumpster pad, WWF reinforced | 222 SF |
| Transformer pad | 27 SF |
| Dumpster enclosure footing concrete | 11.9 CY |
| 4" concrete-filled pipe bollards | 4 EA |
Pricing, markups and owner details stay with the client. The quantities and plan markups on this page are taken unchanged from the delivered estimate.
Send a set of drawings today and receive a bid-ready estimate — accurate, local, and on time. No subscription. No retainer. Just results.