A small, fast-turn scope: sidewalk demolition, new ADA sidewalks and pads, a trench drain and a mezzanine deck topping for an existing pharmacy remodel.
20
Takeoff line items
3
Plan sheets marked
3
Workbook tabs
Under $100K
Package size
Colour-coded takeoff markups from the delivered plan set. Click a sheet to enlarge.
916 SF
Sidewalk removal
897 SF
New 4" sidewalk
971 SF
Reinforced pads
3
ADA sign bollards
8 summary lines rolled up from 20 detailed takeoff items. Measured quantities, before waste.
01Demolition
| Item | Quantity |
|---|---|
| Concrete sidewalk to be removed | 916 SF |
02New site concrete
| Item | Quantity |
|---|---|
| 4" air-entrained 4000 PSI sidewalk | 897 SF |
| 6" reinforced concrete pads | 971 SF |
| 6" dense graded aggregate base | 34.6 CY |
| Trench drain concrete | 0.19 CY |
| Trench drain rebar | 53.1 LB |
| ADA sign on bollards | 3 EA |
03Building
| Item | Quantity |
|---|---|
| 2" concrete topping on composite deck | 46 SF |
Pricing, markups and owner details stay with the client. The quantities and plan markups on this page are taken unchanged from the delivered estimate.